Takt, cycle time and staffing
Available time excludes breaks and planned stops but not unplanned losses, which is why many plants set a planned cycle time a little shorter than takt. Dividing the total work content of one unit by takt time gives the minimum number of operators or stations; the real number is usually higher because tasks cannot be split perfectly, which the line balancing calculator shows. When demand changes, takt changes and the line is rebalanced.
Assumptions and limits
- Demand and available time for the same period.
- Work content is the total manual or station time for one unit.
References
- Rother, M. and Shook, J., Learning to See: Value Stream Mapping to Add Value and Eliminate Muda, Lean Enterprise Institute, 1999.
- Liker, J. K., The Toyota Way: 14 Management Principles from the World's Greatest Manufacturer, McGraw-Hill, 2004.
Questions
- What is the takt time for two 8-hour shifts with 50 minutes of breaks each and a demand of 430 units a day?
- 120 seconds: 860 minutes of available time divided by 430 units.
- How many operators does 9.5 minutes of work content need?
- At least 5: 570 seconds of work over a 120-second takt is 4.75 operators.
Results depend on the figures you enter and on the assumptions listed above. Check carrier tariffs, contracts and customs rulings before relying on them. Read the disclaimer.