Learning Curve Calculator (Unit and Cumulative Average Models)

Learning curves describe how the time or cost per unit falls as cumulative output grows: on an 80% curve, every doubling of output cuts the time to 80% of what it was. They are used to price contracts, plan labor and set realistic targets for new products.

Inputs

%

Results

Time of unit n
51.2
Total for units 1 to n
534.6
Average per unit over 1 to n
66.82
Exponent b
-0.3219

    RefOPS-PRD-005
    Methodb = log₂(learning rate); unit model: Tₙ = T₁·nᵇ; cumulative average model: average of n units = T₁·nᵇ, total = T₁·nᵇ⁺¹
    UnitsSI
    Date2026-11-24

    Working

    Calculated in SI base units; inputs are converted from the units you choose.

    1. Exponentb = log(rate) ÷ log 2log(0.8) ÷ log 2 = -0.3219
    2. Unit nTₙ = T₁ × nᵇ100 × 8^-0.3219 = 51.2
    3. Averagetotal ÷ n534.6 ÷ 8 = 66.82 (66.82% of the first unit)

    At each doubling of output

    UnitUnit timeCumulative totalCumulative average
    1100100100
    28018090
    464314.2103702778560478.55259256946401
    851.2534.591353327031266.8239191658789

    Unit and cumulative average models

    Wright's original 1936 study of aircraft production used the cumulative average model: the average time of all units so far falls by the learning rate at each doubling. The unit model, associated with Crawford and common in operations textbooks, applies the rate to the time of each individual unit. For the same rate the two give different numbers, so state which one an estimate uses. Typical rates depend on how much of the work is manual: the more machine-paced the process, the closer the rate is to 100%.

    Assumptions and limits

    • A constant learning rate over the range of units.
    • No breaks in production that cause forgetting.

    References

    • Wright, T. P., Factors affecting the cost of airplanes, Journal of the Aeronautical Sciences 3(4), 122–128, 1936.
    • Yelle, L. E., The learning curve: historical review and comprehensive survey, Decision Sciences 10(2), 302–328, 1979.
    • Heizer, J., Render, B. and Munson, C., Operations Management: Sustainability and Supply Chain Management, 13th ed., Pearson, 2020 (Module E, Learning Curves).

    Questions

    If the first unit takes 100 hours on an 80% curve, how long does the 8th take?
    51.2 hours under the unit model (100 × 0.8³), and the first eight units take 534.6 hours in total.
    What about the cumulative average model?
    The average of the first eight units is 51.2 hours, so they take 409.6 hours in total, and the 8th unit alone takes 35.5 hours.

    Results depend on the figures you enter and on the assumptions listed above. Check carrier tariffs, contracts and customs rulings before relying on them. Read the disclaimer.