Design, effective and actual capacity
Design capacity is the theoretical maximum, such as a line's rated output running every hour of every shift. Effective capacity is lower because of planned losses: changeovers, maintenance, quality checks and the product mix. Actual output is lower again because of unplanned losses such as breakdowns and shortages. A plant can be efficient (close to effective capacity) while still poorly utilized if effective capacity is far below design. For machine requirements, include setup time per batch, since frequent small batches can need an extra machine.
Assumptions and limits
- Output measured in the same units and period for all capacities.
- In the machines mode, standard times, setups and efficiency are averages over the year.
References
- Heizer, J., Render, B. and Munson, C., Operations Management: Sustainability and Supply Chain Management, 13th ed., Pearson, 2020 (Supplement 7, Capacity and Constraint Management).
- Stevenson, W. J., Operations Management, 14th ed., McGraw-Hill, 2021 (Chapter 5, Strategic Capacity Planning).
Questions
- A bakery line has a design capacity of 201,600 rolls a week, effective capacity 175,000 and actual output 148,000. What are its utilization and efficiency?
- Utilization is 73.4% and efficiency 84.6%.
- How many machines make 60,000 units a year at 6 minutes each with 45-minute setups every 500 units?
- 2 machines: 6,090 hours of work against 3,196 effective hours per machine (3,760 hours at 85%), or 1.91 machines exactly.
Results depend on the figures you enter and on the assumptions listed above. Check carrier tariffs, contracts and customs rulings before relying on them. Read the disclaimer.