OEE Calculator (Overall Equipment Effectiveness)

Overall equipment effectiveness (OEE) is the share of planned production time that is truly productive: making only good parts, as fast as possible, with no stops. It multiplies availability, performance and quality, so it shows which of the three losses to attack first.

Inputs

Results

OEE
74.79%
Availability
88.81
%
Performance
86.11
%
Quality
97.8
%
Run time
373
Fully productive time
314.1
Good pieces
18,848

    RefOPS-PRD-002
    MethodOEE = availability × performance × quality; availability = run time ÷ planned time; performance = ideal cycle time × total count ÷ run time; quality = good count ÷ total count
    UnitsSI
    Date2026-11-24

    Working

    Calculated in SI base units; inputs are converted from the units you choose.

    1. Planned production timeshift − planned stops480 − 60 = 420 min
    2. Availabilityrun time ÷ planned time(420 − 47) ÷ 420 = 88.81%
    3. Performanceideal cycle time × total count ÷ run time1 s × 19,271 ÷ 22,380 s = 86.11%
    4. Qualitygood count ÷ total count18,848 ÷ 19,271 = 97.8%
    5. OEEA × P × Q (= good count × ideal cycle time ÷ planned time)88.81% × 86.11% × 97.8% = 74.79%

    Where the planned time went

    Time categoryMinutes% of planned time
    Availability loss (unplanned stops)4711.190476190476195
    Performance loss (slow running, small stops)51.8166666666666712.337301587301587
    Quality loss (rejects)7.051.6785714285714286
    Fully productive time314.133333333333374.79365079365078

    The three losses

    Availability counts stops during planned production time, such as breakdowns, changeovers and waiting for material. Performance counts running slower than the ideal cycle time, including small stops that are not logged as downtime. Quality counts parts that are scrapped or reworked. OEE equals the good count times the ideal cycle time, divided by the planned production time. Planned stops such as breaks are excluded from OEE by definition; TEEP (total effective equipment performance) measures against all calendar time instead.

    Assumptions and limits

    • One product with a single ideal cycle time; for a mix, use a weighted ideal time.
    • Planned stops are excluded from the planned production time.

    References

    • Nakajima, S., Introduction to TPM: Total Productive Maintenance, Productivity Press, 1988.
    • Vorne Industries, OEE Calculation (oee.com): definitions of availability, performance and quality.

    Questions

    What is the OEE of an 8-hour shift with 60 minutes of breaks, 47 minutes of downtime, a 1-second ideal cycle, 19,271 pieces and 423 rejects?
    74.8%: availability 88.8% (373 of 420 minutes), performance 86.1% and quality 97.8%.
    Which loss is largest in that example?
    Performance: slow running and small stops cost 51.8 minutes, more than the 47 minutes of downtime and the 7.1 minutes of rejected output.

    Results depend on the figures you enter and on the assumptions listed above. Check carrier tariffs, contracts and customs rulings before relying on them. Read the disclaimer.