The three losses
Availability counts stops during planned production time, such as breakdowns, changeovers and waiting for material. Performance counts running slower than the ideal cycle time, including small stops that are not logged as downtime. Quality counts parts that are scrapped or reworked. OEE equals the good count times the ideal cycle time, divided by the planned production time. Planned stops such as breaks are excluded from OEE by definition; TEEP (total effective equipment performance) measures against all calendar time instead.
Assumptions and limits
- One product with a single ideal cycle time; for a mix, use a weighted ideal time.
- Planned stops are excluded from the planned production time.
References
- Nakajima, S., Introduction to TPM: Total Productive Maintenance, Productivity Press, 1988.
- Vorne Industries, OEE Calculation (oee.com): definitions of availability, performance and quality.
Questions
- What is the OEE of an 8-hour shift with 60 minutes of breaks, 47 minutes of downtime, a 1-second ideal cycle, 19,271 pieces and 423 rejects?
- 74.8%: availability 88.8% (373 of 420 minutes), performance 86.1% and quality 97.8%.
- Which loss is largest in that example?
- Performance: slow running and small stops cost 51.8 minutes, more than the 47 minutes of downtime and the 7.1 minutes of rejected output.
Results depend on the figures you enter and on the assumptions listed above. Check carrier tariffs, contracts and customs rulings before relying on them. Read the disclaimer.