Weld Metal, Consumable and Welding Cost Calculator

Estimating a welding job starts with how much weld metal goes into the joints. This calculator works out the weld metal weight for fillet and butt welds, then the consumables to buy, the arc time and total time for the process, and the labour and consumable cost.

Inputs

%
%
%
Advanced options (1)

Results

Weld metal deposited
2.763
Electrode or wire needed
2.909
Arc time
0.9211
Total welding time
2.303
Labour plus consumable cost
103.7
Weld cross-section area
35.2

    RefENG-WLD-003
    MethodWeld area × length × density; consumable = weld metal / deposition efficiency; arc time = weld metal / deposition rate
    UnitsSI
    Date2026-11-23

    Working

    Calculated in SI base units; inputs are converted from the units you choose.

    1. Weld area with reinforcementA = z²/2A = 35.2 mm²
    2. Weld metalm = A·L·ρm = 2.763 kg
    3. Consumable and timeconsumable 2.909 kg; arc time 0.9211 h; total 2.303 h

    Where the cost is

    Labour usually makes up 70 to 85 % of welding cost, so deposition rate and operating factor matter far more than consumable price. Moving from SMAW to FCAW or SAW often halves the cost of a joint.

    Assumptions and limits

    • Steel weld metal; nominal joint dimensions.
    • Typical deposition data; check with the consumable data sheet.

    References

    • AWS Welding Handbook, volume 1, chapter on welding economics.
    • TWI Job Knowledge guides on weld costing.

    Questions

    How much weld metal is in 10 m of 8 mm fillet weld?
    About 2.8 kg with 10 % for convexity; GMAW needs about 2.9 kg of wire.
    What is a typical operating factor?
    About 20 to 30 % for manual SMAW, 30 to 50 % for semi-automatic GMAW or FCAW, and 50 % or more for mechanised SAW.

    This calculator is a design aid. Check results against the governing code or standard and have critical work verified by a qualified engineer. Read the disclaimer.