Lead time demand and safety stock
If you sell an average of 40 units a day and the supplier takes 7 days, you expect to sell 280 units while waiting, so with no safety stock you would reorder at 280. Demand is never exactly average, so safety stock is added. With normally distributed daily demand, safety stock is z × σd × √L, where z comes from the service level: about 1.28 for 90%, 1.64 for 95% and 2.33 for 99%. Count stock on order as well as on hand when comparing with the reorder point if the lead time is longer than the time between orders.
Assumptions and limits
- Continuous review: stock is checked all the time and an order placed as soon as it reaches the reorder point.
- Daily demand independent from day to day and roughly normal; lead time fixed in the service-level mode.
References
- Heizer, J., Render, B. and Munson, C., Operations Management: Sustainability and Supply Chain Management, 13th ed., Pearson, 2020 (Chapter 12, reorder points and safety stock).
- Chopra, S. and Meindl, P., Supply Chain Management: Strategy, Planning, and Operation, 6th ed., Pearson, 2016 (Chapter 12, safety inventory).
Questions
- What is the reorder point for 40 units a day, a 7-day lead time and a 95% service level with σ = 12 units a day?
- About 332 units: 280 units of lead-time demand plus 52 units of safety stock (1.645 × 12 × √7).
- What is the reorder point without safety stock?
- The lead-time demand alone, 280 units in the example. Half of all cycles would then run out before the delivery arrives.
Results depend on the figures you enter and on the assumptions listed above. Check carrier tariffs, contracts and customs rulings before relying on them. Read the disclaimer.