Safety
Trenches deeper than about 1.2 to 1.5 m need sloping, benching or shoring under most safety regulations. The side slope input lets you include battered sides in the quantity; it does not check stability.
Assumptions and limits
- Flat ground; constant depth and side slope.
- Typical swell factors; compacted fill will shrink below bank volume.
References
- Peurifoy, R. L., Construction Planning, Equipment, and Methods.
- OSHA 29 CFR 1926 Subpart P, Excavations.
Questions
- How much soil comes out of a 20 m trench, 1 m wide and 1.5 m deep with 0.5:1 sides?
- About 55 m³ in the ground and about 71 m³ loose for clay, which is 8 loads of a 10 m³ truck.
- What is the swell factor?
- The increase in volume when soil is dug: around 10 to 15 % for sand, 25 to 40 % for clay, and up to 50 to 60 % for blasted rock.
This calculator is a design aid. Check results against the governing code or standard and have critical work verified by a qualified engineer. Read the disclaimer.