Why the draw schedule matters
Interest is charged only on money already released, so early draws cost the most. A build that runs late adds months of interest at the highest balance. Lenders release draws after inspections of completed stages, and many construction-to-permanent loans then convert automatically to a mortgage at a rate fixed at the start or at completion.
Assumptions and limits
- Draws are released at the start of the month entered; interest-only payments monthly at a fixed rate.
- Fees, inspection costs and contingency reserves are not included.
References
- Geltner, D. M., Miller, N. G., Clayton, J. and Eichholtz, P., Commercial Real Estate Analysis and Investments, construction loans and draws.
- Brealey, R. A., Myers, S. C. and Allen, F., Principles of Corporate Finance, loan amortization.
Questions
- What interest does a 500,000 construction loan at 8% cost over a 12-month build?
- With draws of 20%, 20%, 25%, 25% and 10% at months 0, 2, 4, 7 and 10, the average amount drawn is 327,083.33 and the interest during construction is 26,166.67. The permanent mortgage at 7% over 30 years then costs 3,326.51 a month.
- Do I pay interest on the full loan from the start?
- No, only on the amount drawn so far, which is why the payments grow as the build progresses.