Using L = λW
In a factory, L is the work in progress, λ the throughput and W the flow (cycle) time: with 100 jobs on the floor and 20 finished per hour, a job spends 5 hours in the plant on average. To cut lead time without losing throughput, cut work in progress. In inventory terms, average stock divided by the rate of use gives the average time an item spends in stock, the idea behind days of inventory. All three quantities must use the same units and the same boundary of the system, and the system must be stable over the period, with arrivals and departures balancing.
Assumptions and limits
- Long-run averages for a stable system (arrival rate equals departure rate).
- L, λ and W measured over the same period and for the same system boundary.
References
- Little, J. D. C., A proof for the queuing formula: L = λW, Operations Research 9(3), 383–387, 1961.
- Hopp, W. J. and Spearman, M. L., Factory Physics, 3rd ed., Waveland Press, 2011.
Questions
- A plant has 100 jobs in progress and finishes 20 an hour. How long does a job take?
- 5 hours on average (100 ÷ 20).
- A clinic sees 12 patients an hour and each spends 45 minutes inside. How many are there on average?
- 9 patients (12 per hour × 0.75 hours).
Results depend on the figures you enter and on the assumptions listed above. Check carrier tariffs, contracts and customs rulings before relying on them. Read the disclaimer.